Case Study

SCADA and Communication Site Audit

The Auditing of Water Corporation assets was conducted between January 2021 and February2022. These assets were audited due to the 3G network being scaled back in the near future. The upgrade of equipment will be to change to 4G ready equipment or IP Radios if there is no 4G signal present at the site. This is the case where some of the assets are located a long distance from the main townsite in the region. We audited various areas from Esperance to Wyndham and many locations in between.

The type of sites audited:

  • Bore sites
  • Sewerage Pumping Station
  • Water Pumping Station
  • Tank sites
  • Chlorination Modules